Billion-dollar LNG terminal in full production in Mississippi

MississippiOctober 27, 2011 

PASCAGOULA — In front of tanks already filled with liquefied natural gas, executives will cut the ribbon at the Gulf LNG Energy terminal at the Port of Pascagoula today to mark the completion of the $1.1 billion project.

Gov. Haley Barbour will join John McCutchen, Gulf LNG Energy chief operations officer, at noon for the ceremony at the terminal at Bayou Casotte on Industrial Road. Sen. Roger Wicker and county and city officials also will be on hand.

Six ships have already transported their loads to the terminal’s two low-pressure storage tanks, which are capable of holding 6.6 billion cubic feet of liquefied gas, a clean-burning fossil fuel that is produced and exported by countries whose natural gas reserves exceed their demand.

The terminal is capable of sending out 1.3 billion cubic feet per day of the regasified product, by way of various pipelines crisscrossing the Southern states, he said.

The gas is lighter than air, and if released would evaporate and dissipate into the atmosphere, he said.

It is liquefied to save money on transportation, he said. Cooled to minus 260 degrees, the liquid natural gas is reduced in volume by 600 to 1.

“It would take 600 ships to haul that same quantity in gas form compared to what it is in liquid form,” he said.

Read the complete story at sunherald.com

McClatchy Washington Bureau is pleased to provide this opportunity to share information, experiences and observations about what's in the news. Some of the comments may be reprinted elsewhere in the site or in the newspaper. We encourage lively, open debate on the issues of the day, and ask that you refrain from profanity, hate speech, personal comments and remarks that are off point. Thank you for taking the time to offer your thoughts.