Judges OK delay of Calif. nuclear plant's license

The TribuneJune 9, 2011 

A panel of three federal administrative law judges has announced it is delaying Diablo Canyon nuclear power plant’s license renewal until at least December 2015.

The Nuclear Regulatory Commission’s Atomic Safety and Licensing Board on Tuesday put NRC staff and PG&E on notice that it cannot make a decision on license renewal until detailed seismic studies of faults around the plant are complete and ordered the utility to submit monthly reports starting in July on the status of those studies.

The ruling confirmed a decision last week by the NRC to delay license renewal until seismic studies are done and added new reporting requirements.

Read the full story at sanluisobispo.com.

McClatchy Washington Bureau is pleased to provide this opportunity to share information, experiences and observations about what's in the news. Some of the comments may be reprinted elsewhere in the site or in the newspaper. We encourage lively, open debate on the issues of the day, and ask that you refrain from profanity, hate speech, personal comments and remarks that are off point. Thank you for taking the time to offer your thoughts.

Commenting FAQs | Terms of Service