Illinois' Prairie State Energy Campus aims to be very 'green'

email this story print this story jump to comments

The Prairie State Energy Campus under construction in Washington County is expected to begin generation by the end of the year.

By December, the first of two energy-generating units at the $4 billion power plant should be ready to go online. The second is anticipated to begin by summer 2012.

Together, the two will generate 1,600 megawatts of electricity that will reach more than 2.5 million customers in eight states using what has been advertised as "clean, low-cost electricity."

Designed with the latest technology, the power plant's carbon dioxide emissions will be approximately 15 percent lower than what is typically discharged from U.S. coal-fueled plants.

The coal that will fuel the plant is coming from the adjacent Lively Grove Mine, thus eliminating the carbon emissions associated with coal transportation.

Read the complete story at bnd.com

  • Bookmark and Share
  • email
  • |
  • print
  • |
  • rss

tool name

close
tool goes here
JOIN THE DISCUSSION

We welcome comments. To post one, you must sign in using either your McClatchyDC login or your login for Facebook, Twitter or Disqus. Just click the appropriate box below.

Please keep your comment civil, short and to the point. Obscene, profane, abusive and off topic comments will be deleted. Repeat offenders will be blocked. If you find a comment abusive or inappropriate, please flag it for the moderator by placing your cursor on the comment, then clicking the "flag" link that appears. Thanks for your participation.

Stay Connected

Sign up for email newsletters RSS
Follow us on your iPhone Follow us on your Android device
Follow us on Facebook Follow us on Twitter Follow us using Google Currents